Tuesday, February 21, 2012

4 days more...

On a hot day, with only a few sun showers, several more tasks were accomplished:
  • The roof is ON!
  • The installation of the ceilings and wiring continues. Once we have power, we can work even later to finish up the tasks... until then, when darkness falls, most of us must stop.
  • The outside walls have been painted
  • The windows are in, and many of the window sills have been completed.
  • The base of the septic system was poured so tomorrow they can build the rest of it.
  • Doors are beginning to be hung
  • and more and more painting...if it doesn't move, it will be painted by weeks end!


One final note,

One of our team members was speaking with one of our very quiet masons today. She asked if he enjoyed working with our team. He said he enjoyed it very much. He liked the feeling of being proud in what he was building and working with the group. It is rewarding to know that they  have understood our efforts to make them a part of the overall group, and that they understand and share the passion for our work.

Good night everyone!