Due to somewhat faster progress than anticipated on other projects, a few of us had the privilege of going to the Checker Hall Corps and Daycare to do a few minor projects to refresh the facility and repair roof leaks to prevent future issues... AND .... we were able to participate in the children's morning devotions and play ... just a bit :-)
A Work summary update from our Project Manager Joel:
1) Remove and replace vinyl floor tile in kitchen (110
sq. ft.)
2)
Remove, replace and grout ceramic tiles in daycare play area
3)
Remove damaged ceiling in bathroom
-Replace
with new plywood
-Prime
and paint
4)
Minor repairs to louvers and doors
-Paint
doors and trim
5)
Metal flashing on concrete parapets
-Measure
and order metal
-Install
on front and back of church (80 lin. Ft.)
6)
Paint areas of daycare, `Big Bird` and 'Tweety Bird' door murals:
-Paint
room dividers
-Paint
chairs and benches
7)
Kitchen
-Repair
kitchen counter
-Paint
kitchen
8)
Repairs to plumbing, new toilet seats